If you love Faversham, join us. We seek to Cherish the Past, Adorn the Present, Create for the Future

Cleve Hill: Demand for Solar Power

Submission on behalf of the Faversham Society on the Need for CHSP -  Deadline 3\

  1. Introduction
    We recognise the urgent need to decarbonise electricity generation in the UK as outlined in the applicant’s Statement of Need and Addendum submission. This paper considers the deployment projections for solar PV currently in planning against deployment projections for requirements of solar PV by the National Grid, the UK System Operator.

    Comparing a case including the generating capacity of Cleve Hill against one excluding Cleve Hill, it concludes that the Solar PV deployments will be exceeded without the Cleve Hill site, thus concluding that there is not a need Cleve Hill Solar Park.

    2. National Grid Future Energy Scenarios
    National Grid in its role as the UK’s System Operator managing the electricity grid, prepares annual forecasts known as the Future Energy Scenarios (FES) (http://fes.nationalgrid.com/fes-document/). This sets out the three different scenarios it considers most likely given energy demand, expectations for electricity supply, current policies, decarbonisation requirements and requirements of energy security. The most recent version is FES 2019 published in July, just before the ISH on Need. FES 2018 enables detailed forecast demand figures to be extracted up to 2030. A careful study of FES 2019 reveals that it differs only in that it takes account of a proposed zero carbon target by 2050.  However, for the period up to 2030 FES 2019 is identical to FES 2018. We have therefore used the detailed figures from FES 2018 in this submission. We discuss the impact of the new zero-carbon policy framework in 4. below. The three scenarios identified and fully explained in FES 2018 and 2019 are:

    Community Renewables
    Two Degrees
    Steady Progression
    Consumer Evolution

3.The UK solar market
Many markets globally have ended direct subsidies in favour of unsubsidised markets or auction processes where governments procure electricity from the least expensive plants available. This has all driven the requirement for PV to become competitive with other forms of generation. The supply chain has responded in improving production efficiencies of PV systems and their constituent parts, resulting in reductions in capex of PV plants globally.

Given the costs reductions currently in train, the initial costs of installing solar PV in the UK are currently estimated to be c. £400-500k/MW. Given these prices, UK solar is now on the verge of cost competitiveness, and as these cost reductions continue, it is widely considered that it will be competitive with other generation within months.

The UK solar industry is responding and localised solar PV development is increasing with many development and construction cycles which are much shorter than those for other forms of renewable generation. This is especially so for those under the less than 50MW devolved planning process undertaken for all solar PV generation to date. CHSP is the first and only PV plant to be going through the NSIP process.

Submissions in local planning portals provide an accurate estimate of the solar PV projects that are currently in development. These can be considered in conjunction with those in pre-application and consultation phases to give a reliable indication of solar PV coming on stream over the period 2019-2022.

4. FES 2019 and Zero Carbon by 2050

As noted above, FES 2019 takes account of the new policy framework and target for zero carbon by 2050. FES 2019, Fig 5.4 indicates a 2050 solar capacity (demand) of c52GW of which only 42% is centralised. Moreover, FES 2019, Fig.3.2 on decentralisation is also of interest since it indicates that for the Community Renewables scenario, total centralised capacity stays fairly constant right up to 2050. This indicates that even in the zero-carbon scenario there is no role to be played for massive centralised installations such as CHSP. FES 2019  projections also detail and take account of significant energy demand reduction measures up to 2050.

5.Conclusion The chart below shows the total estimated new generating capacity outlined by National Grid in each of the National Grid deployment scenarios described above over the four-year period 2019 to 2022

As shown in Table 2  above the highest deployment projection for solar currently envisaged by National Grid (Community Renewables) is 4.1 GW from 2019 to 2022. Even without new additional solar PV, which will inevitably come on line in the coming years, the estimated capacity currently in planning (Table 3), excluding Cleve Hill is 4.3 GW which exceeds this projection. In addition the trend is away from centralised generating capacity such as Cleve Hill.

This indicates that by the planned completion date for CHSP there will already be sufficient solar PV capacity in the UK to meet our projected energy and decarbonisation needs.

This establishes conclusively that CHSP is not needed and will be redundant before it is completed.

Professor Sir David Melville CBE, BSc, PhD, CPhys, FInstP, Sen Mem IEEE(USA)

Vice-Chair

The Faversham Society

July 27, 2019

Leave a Reply

Opening Times

VISITOR INFORMATION CENTRE
12 Market Place, ME13 7AE
10am to 4pm - Monday to Saturday
10am to 1pm - Sunday (opening hours may vary)

FLEUR MUSEUM - FREE ENTRY
12-13 Preston Street, ME13 8NS
Open Fridays & Saturdays 11:00 to 15:00

SECOND-HAND BOOKSHOP
11 Preston Street, ME13 8NS
10am to 3.30pm - Monday to Saturday

CHART MILLS
Off Stonebridge Way, ME13 7SE

Open Saturday and Sunday from 2-5pm

Registered Charity  Number 1135262 - Company No 07112241
The Faversham Society - Registered Address: 10-13 Preston Street, Faversham, Kent ME13 8NS
linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram